{"id":363,"date":"2025-09-05T07:01:58","date_gmt":"2025-09-05T07:01:58","guid":{"rendered":"https:\/\/bimtraining.institute\/blog\/?p=363"},"modified":"2025-09-05T07:01:59","modified_gmt":"2025-09-05T07:01:59","slug":"oakland-international-airport-bim-case-study","status":"publish","type":"post","link":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/","title":{"rendered":"Oakland International Airport, USA \u2013 BIM Case Study"},"content":{"rendered":"\n<h3 class=\"wp-block-heading\">Introduction<\/h3>\n\n\n\n<p>Airports are among the most complex infrastructures in the world, requiring careful planning, coordination, and execution. The <strong>Oakland International Airport in California, USA<\/strong>, is an excellent example of how <strong>Building Information Modeling (BIM)<\/strong> revolutionized airport expansion and renovation projects. With multiple stakeholders involved\u2014including architects, engineers, contractors, and facility managers\u2014BIM played a vital role in ensuring smooth collaboration, cost efficiency, and on-time project delivery.<\/p>\n\n\n\n<figure class=\"wp-block-image size-large\"><img fetchpriority=\"high\" decoding=\"async\" width=\"1024\" height=\"1024\" src=\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18-1024x1024.jpg\" alt=\"3D BIM model of Oakland International Airport terminal expansion\" class=\"wp-image-364\" srcset=\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18-1024x1024.jpg 1024w, https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18-300x300.jpg 300w, https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18-150x150.jpg 150w, https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18-768x768.jpg 768w, https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg 1080w\" sizes=\"(max-width: 1024px) 100vw, 1024px\" \/><\/figure>\n\n\n\n<hr class=\"wp-block-separator has-alpha-channel-opacity\"\/>\n\n\n\n<h3 class=\"wp-block-heading\">The Need for BIM in Oakland International Airport<\/h3>\n\n\n\n<p>The Oakland International Airport faced challenges such as:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li>Expanding terminal capacity to handle increasing passenger demand.<\/li>\n\n\n\n<li>Modernizing facilities to meet sustainability and safety standards.<\/li>\n\n\n\n<li>Reducing project delays and minimizing disruption to ongoing airport operations.<\/li>\n\n\n\n<li>Coordinating multiple design and construction teams across a massive infrastructure project.<\/li>\n<\/ul>\n\n\n\n<p>Traditional design and construction methods would have led to <strong>clash conflicts, delays, and cost overruns<\/strong>. This is where BIM came in as a game-changer.<\/p>\n\n\n\n<hr class=\"wp-block-separator has-alpha-channel-opacity\"\/>\n\n\n\n<h3 class=\"wp-block-heading\">How BIM Was Implemented<\/h3>\n\n\n\n<p>The project team used <strong>3D, 4D, and 5D BIM<\/strong> models to manage and streamline every stage of construction:<\/p>\n\n\n\n<ol class=\"wp-block-list\">\n<li><strong>3D Modeling &amp; Clash Detection<\/strong>\n<ul class=\"wp-block-list\">\n<li>Engineers created detailed 3D models of structural, mechanical, electrical, and plumbing systems.<\/li>\n\n\n\n<li>Clash detection was performed to identify and resolve conflicts between different building systems before actual construction, preventing costly rework.<\/li>\n<\/ul>\n<\/li>\n\n\n\n<li><strong>4D BIM for Scheduling<\/strong>\n<ul class=\"wp-block-list\">\n<li>The project team linked the BIM model with construction schedules, creating a <strong>time-lapse sequence<\/strong> of construction activities.<\/li>\n\n\n\n<li>This allowed better planning of work sequences, minimizing disruption to airport operations.<\/li>\n<\/ul>\n<\/li>\n\n\n\n<li><strong>5D BIM for Cost Management<\/strong>\n<ul class=\"wp-block-list\">\n<li>Cost estimates were directly integrated into the BIM model.<\/li>\n\n\n\n<li>Any design change instantly updated the cost implications, ensuring <strong>real-time budget control<\/strong>.<\/li>\n<\/ul>\n<\/li>\n\n\n\n<li><strong>Collaboration &amp; Data Sharing<\/strong>\n<ul class=\"wp-block-list\">\n<li>All stakeholders had access to a shared BIM platform, improving communication and reducing errors.<\/li>\n\n\n\n<li>Contractors and facility managers could review digital models to understand site constraints and plan accordingly.<\/li>\n<\/ul>\n<\/li>\n<\/ol>\n\n\n\n<hr class=\"wp-block-separator has-alpha-channel-opacity\"\/>\n\n\n\n<h3 class=\"wp-block-heading\">Benefits of BIM in the Oakland International Airport Project<\/h3>\n\n\n\n<p>The adoption of BIM led to remarkable benefits:<\/p>\n\n\n\n<ul class=\"wp-block-list\">\n<li><strong>Reduced Construction Delays<\/strong> \u2013 With 4D scheduling, disruptions to daily airport operations were minimized.<\/li>\n\n\n\n<li><strong>Lower Costs<\/strong> \u2013 Clash detection and 5D cost integration saved millions in potential rework and material wastage.<\/li>\n\n\n\n<li><strong>Enhanced Safety<\/strong> \u2013 Virtual simulations allowed the project team to plan site safety measures effectively.<\/li>\n\n\n\n<li><strong>Improved Sustainability<\/strong> \u2013 Energy modeling and optimized designs helped meet sustainability goals.<\/li>\n\n\n\n<li><strong>Better Facility Management<\/strong> \u2013 The as-built BIM model became a valuable resource for long-term maintenance of the airport.<\/li>\n<\/ul>\n\n\n\n<hr class=\"wp-block-separator has-alpha-channel-opacity\"\/>\n\n\n\n<h3 class=\"wp-block-heading\">Key Lessons from Oakland International Airport BIM Case Study<\/h3>\n\n\n\n<p>The project highlighted a few important takeaways:<\/p>\n\n\n\n<ol class=\"wp-block-list\">\n<li><strong>BIM ensures smoother coordination<\/strong> across multi-disciplinary teams in large-scale infrastructure projects.<\/li>\n\n\n\n<li><strong>Digital construction reduces risks<\/strong>, saving both time and money.<\/li>\n\n\n\n<li><strong>Airports worldwide can replicate this model<\/strong> to achieve efficient, sustainable, and disruption-free expansions.<\/li>\n<\/ol>\n\n\n\n<hr class=\"wp-block-separator has-alpha-channel-opacity\"\/>\n\n\n\n<h3 class=\"wp-block-heading\">Conclusion<\/h3>\n\n\n\n<p>The <strong>Oakland International Airport BIM case study<\/strong> proves how powerful digital tools can transform complex infrastructure projects. From clash detection to cost management, BIM helped streamline one of the busiest airports in California, ensuring long-term value for both stakeholders and passengers.<\/p>\n\n\n\n<p>As airports continue to grow globally, <strong>BIM will remain an indispensable technology<\/strong> for creating smarter, safer, and more efficient transport hubs.<\/p>\n","protected":false},"excerpt":{"rendered":"<p>Introduction Airports are among the most complex infrastructures in the world, requiring careful planning, coordination, and execution. The Oakland International [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":364,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"default","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"disabled","footer-sml-layout":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"footnotes":""},"categories":[1],"tags":[],"class_list":["post-363","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-blog"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v25.5 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Oakland International Airport BIM Case Study | Smart Construction<\/title>\n<meta name=\"description\" content=\"Discover how Oakland International Airport used BIM for design, clash detection, scheduling, and cost management. Learn how BIM reduced delays, improved safety, and enhanced efficiency in airport construction.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Oakland International Airport BIM Case Study | Smart Construction\" \/>\n<meta property=\"og:description\" content=\"Discover how Oakland International Airport used BIM for design, clash detection, scheduling, and cost management. Learn how BIM reduced delays, improved safety, and enhanced efficiency in airport construction.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\" \/>\n<meta property=\"og:site_name\" content=\"EduCADD BIM Training Institute\" \/>\n<meta property=\"article:published_time\" content=\"2025-09-05T07:01:58+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2025-09-05T07:01:59+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg\" \/>\n\t<meta property=\"og:image:width\" content=\"1080\" \/>\n\t<meta property=\"og:image:height\" content=\"1080\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"support\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"support\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"3 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#article\",\"isPartOf\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\"},\"author\":{\"name\":\"support\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/#\/schema\/person\/1e030f75be2f6c1d6e0dbfa0c9d62abb\"},\"headline\":\"Oakland International Airport, USA \u2013 BIM Case Study\",\"datePublished\":\"2025-09-05T07:01:58+00:00\",\"dateModified\":\"2025-09-05T07:01:59+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\"},\"wordCount\":500,\"commentCount\":0,\"publisher\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/#organization\"},\"image\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg\",\"articleSection\":[\"Blog\"],\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"CommentAction\",\"name\":\"Comment\",\"target\":[\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#respond\"]}]},{\"@type\":\"WebPage\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\",\"url\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\",\"name\":\"Oakland International Airport BIM Case Study | Smart Construction\",\"isPartOf\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage\"},\"image\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage\"},\"thumbnailUrl\":\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg\",\"datePublished\":\"2025-09-05T07:01:58+00:00\",\"dateModified\":\"2025-09-05T07:01:59+00:00\",\"description\":\"Discover how Oakland International Airport used BIM for design, clash detection, scheduling, and cost management. Learn how BIM reduced delays, improved safety, and enhanced efficiency in airport construction.\",\"breadcrumb\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage\",\"url\":\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg\",\"contentUrl\":\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg\",\"width\":1080,\"height\":1080},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/bimtraining.institute\/blog\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Oakland International Airport, USA \u2013 BIM Case Study\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/#website\",\"url\":\"https:\/\/bimtraining.institute\/blog\/\",\"name\":\"BIM Training Institute\",\"description\":\"\",\"publisher\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/bimtraining.institute\/blog\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/#organization\",\"name\":\"EduCADD\",\"url\":\"https:\/\/bimtraining.institute\/blog\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/#\/schema\/logo\/image\/\",\"url\":\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/07\/cropped-EduCADD-Logo-63955384-512d-45ef-b03c-55a42d020ffb-1.png\",\"contentUrl\":\"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/07\/cropped-EduCADD-Logo-63955384-512d-45ef-b03c-55a42d020ffb-1.png\",\"width\":331,\"height\":103,\"caption\":\"EduCADD\"},\"image\":{\"@id\":\"https:\/\/bimtraining.institute\/blog\/#\/schema\/logo\/image\/\"}},{\"@type\":\"Person\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/#\/schema\/person\/1e030f75be2f6c1d6e0dbfa0c9d62abb\",\"name\":\"support\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\/\/bimtraining.institute\/blog\/#\/schema\/person\/image\/\",\"url\":\"https:\/\/secure.gravatar.com\/avatar\/1b43eb586030270585e01c4b38a188e1ae6f33e91a125e4c2466a46cd2f9ccad?s=96&d=mm&r=g\",\"contentUrl\":\"https:\/\/secure.gravatar.com\/avatar\/1b43eb586030270585e01c4b38a188e1ae6f33e91a125e4c2466a46cd2f9ccad?s=96&d=mm&r=g\",\"caption\":\"support\"},\"sameAs\":[\"https:\/\/bimtraining.institute\/blog\"],\"url\":\"https:\/\/bimtraining.institute\/blog\/author\/support\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Oakland International Airport BIM Case Study | Smart Construction","description":"Discover how Oakland International Airport used BIM for design, clash detection, scheduling, and cost management. Learn how BIM reduced delays, improved safety, and enhanced efficiency in airport construction.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/","og_locale":"en_US","og_type":"article","og_title":"Oakland International Airport BIM Case Study | Smart Construction","og_description":"Discover how Oakland International Airport used BIM for design, clash detection, scheduling, and cost management. Learn how BIM reduced delays, improved safety, and enhanced efficiency in airport construction.","og_url":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/","og_site_name":"EduCADD BIM Training Institute","article_published_time":"2025-09-05T07:01:58+00:00","article_modified_time":"2025-09-05T07:01:59+00:00","og_image":[{"width":1080,"height":1080,"url":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg","type":"image\/jpeg"}],"author":"support","twitter_card":"summary_large_image","twitter_misc":{"Written by":"support","Est. reading time":"3 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#article","isPartOf":{"@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/"},"author":{"name":"support","@id":"https:\/\/bimtraining.institute\/blog\/#\/schema\/person\/1e030f75be2f6c1d6e0dbfa0c9d62abb"},"headline":"Oakland International Airport, USA \u2013 BIM Case Study","datePublished":"2025-09-05T07:01:58+00:00","dateModified":"2025-09-05T07:01:59+00:00","mainEntityOfPage":{"@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/"},"wordCount":500,"commentCount":0,"publisher":{"@id":"https:\/\/bimtraining.institute\/blog\/#organization"},"image":{"@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage"},"thumbnailUrl":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg","articleSection":["Blog"],"inLanguage":"en-US","potentialAction":[{"@type":"CommentAction","name":"Comment","target":["https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#respond"]}]},{"@type":"WebPage","@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/","url":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/","name":"Oakland International Airport BIM Case Study | Smart Construction","isPartOf":{"@id":"https:\/\/bimtraining.institute\/blog\/#website"},"primaryImageOfPage":{"@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage"},"image":{"@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage"},"thumbnailUrl":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg","datePublished":"2025-09-05T07:01:58+00:00","dateModified":"2025-09-05T07:01:59+00:00","description":"Discover how Oakland International Airport used BIM for design, clash detection, scheduling, and cost management. Learn how BIM reduced delays, improved safety, and enhanced efficiency in airport construction.","breadcrumb":{"@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#primaryimage","url":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg","contentUrl":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/09\/BIM-Blog-post-18.jpg","width":1080,"height":1080},{"@type":"BreadcrumbList","@id":"https:\/\/bimtraining.institute\/blog\/oakland-international-airport-bim-case-study\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/bimtraining.institute\/blog\/"},{"@type":"ListItem","position":2,"name":"Oakland International Airport, USA \u2013 BIM Case Study"}]},{"@type":"WebSite","@id":"https:\/\/bimtraining.institute\/blog\/#website","url":"https:\/\/bimtraining.institute\/blog\/","name":"BIM Training Institute","description":"","publisher":{"@id":"https:\/\/bimtraining.institute\/blog\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/bimtraining.institute\/blog\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/bimtraining.institute\/blog\/#organization","name":"EduCADD","url":"https:\/\/bimtraining.institute\/blog\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/bimtraining.institute\/blog\/#\/schema\/logo\/image\/","url":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/07\/cropped-EduCADD-Logo-63955384-512d-45ef-b03c-55a42d020ffb-1.png","contentUrl":"https:\/\/bimtraining.institute\/blog\/wp-content\/uploads\/2025\/07\/cropped-EduCADD-Logo-63955384-512d-45ef-b03c-55a42d020ffb-1.png","width":331,"height":103,"caption":"EduCADD"},"image":{"@id":"https:\/\/bimtraining.institute\/blog\/#\/schema\/logo\/image\/"}},{"@type":"Person","@id":"https:\/\/bimtraining.institute\/blog\/#\/schema\/person\/1e030f75be2f6c1d6e0dbfa0c9d62abb","name":"support","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/bimtraining.institute\/blog\/#\/schema\/person\/image\/","url":"https:\/\/secure.gravatar.com\/avatar\/1b43eb586030270585e01c4b38a188e1ae6f33e91a125e4c2466a46cd2f9ccad?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/1b43eb586030270585e01c4b38a188e1ae6f33e91a125e4c2466a46cd2f9ccad?s=96&d=mm&r=g","caption":"support"},"sameAs":["https:\/\/bimtraining.institute\/blog"],"url":"https:\/\/bimtraining.institute\/blog\/author\/support\/"}]}},"_links":{"self":[{"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/posts\/363","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/comments?post=363"}],"version-history":[{"count":1,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/posts\/363\/revisions"}],"predecessor-version":[{"id":365,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/posts\/363\/revisions\/365"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/media\/364"}],"wp:attachment":[{"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/media?parent=363"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/categories?post=363"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/bimtraining.institute\/blog\/wp-json\/wp\/v2\/tags?post=363"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}